Ferry terminal upgrades in Crofton are scheduled to proceed, but BC Ferries must first obtain several approvals, including a noise exemption.
According to the Municipality of North Cowichan, BC Ferries has applied for permission to allow construction noise outside permitted hours. The ferry operator said the exemption is needed to ensure the work proceeds on schedule.
North Cowichan’s noise bylaw currently restricts construction activity during certain hours.
“Erecting, demolishing, or repairing of any building or structure, or the excavation of any land, street, highway, or lane prior to 7:00 a.m. or after 8:00 p.m. on Monday to Saturday, inclusive, or prior to 9:00 a.m. or after 6:00 p.m. on Sundays in such a manner to disturb the peace, quiet, rest, enjoyment, comfort, or convenience of any person or persons in the neighbourhood or vicinity”
Council is expected to vote on a proposed exemption that would allow intermittent night-shift work based on operational needs. The exemption would also require BC Ferries to provide at least one week’s notice to the municipality and nearby residents before work begins and to mitigate overnight noise.
A staff report said approving the exemption would allow BC Ferries to maintain an efficient construction schedule. If council denies the request, the report said the project could face delays and potential impacts to ferry service.
If approved, the exemption would be in effect from May 4 to April 30, 2027.
Once complete, the upgrades would accommodate two Island-class ferry vessels, increase capacity by 20 per cent and transition the route to a two-ship service next year.
Council is expected to vote on the proposed exemption April 15.